GA1 Form Explained: Thorough Examinations of Lifting Equipment in Ireland – 6 or 12 Months?
What the HSA's GA1 form records, the Schedule 1 periods for each type of equipment, what happens when a defect is found, the weekly check on site – and a 12-month examination calendar for a small fleet.
Contents
- What a GA1 form is – and what it is not
- LOLER vs the Irish 2007 Regulations
- How often: 6 months, 12 months and 4-yearly tests
- Defects, deadlines and taking equipment out of use
- Weekly checks on construction sites
- Worked example: a 12-month examination calendar for a small fleet
- Hired-in equipment: what to ask the hire company for
- The register, the reports and how long to keep them
The GA1 form is the Health and Safety Authority's template for a report of thorough examination of lifting equipment, filled in and signed by a competent person. The legal duty behind it is in the Safety, Health and Welfare at Work (General Application) Regulations 2007: lifting accessories, hoists, MEWPs and anything that lifts people must be thoroughly examined at least every 6 months, and cranes, forklifts, telehandlers and vehicle lifts at least every 12 months. Mobile cranes and winches also need a test every 4 years.
The problem is rarely the examination itself but everything around it: the GA1s sit in a folder, the shackles miss the last round, and the hired telehandler's examination runs out a week before it goes back. Equipment past its examination date must not be used (Reg. 52(3)).
What a GA1 form is – and what it is not
The HSA publishes the GA1, GA2 and GA3 (plus a scaffold GA3) on its forms page. All three carry the same note: it is not an approved or statutory form, and reports may be produced in other formats. What the law fixes is the content, not the layout.
| Form | What it records | Legal basis |
|---|---|---|
| GA1 (revision 2012) | Report of thorough examination and testing of lifting equipment, by a competent person | Regs. 52–53 and Schedule 1, Part E |
| GA2 | Weekly examination of lifting equipment used on construction sites | Reg. 43(1)(f) |
| GA3 | Inspections of work equipment for work at height – scaffolds, platforms, ladders, fall protection | Reg. 119 |
Schedule 1, Part E lists what every report must contain: the employer or owner and where the examination took place, the item and its safe working load for each configuration, the purpose of the examination, any defect that is or could become a danger and the repairs needed, parts that could not be reached, the latest date for the next thorough examination, and the examiner's name, address and qualifications. A report from your insurer's engineer that covers all of this is just as valid as a GA1.
People often call it a "GA1 cert", but a GA1 is not a certificate of conformity. Nor is it the certificate of test and examination needed before fixed lifting equipment or a new lifting accessory is first used (Regs. 52(1)(a) and 57). It records the condition of the equipment on the day it was examined.
LOLER vs the Irish 2007 Regulations
LOLER – the Lifting Operations and Lifting Equipment Regulations 1998 – is UK law, and Northern Ireland has its own LOLER (NI) 1999. In the Republic, the rules are in Part 2, Chapter 2 of S.I. No. 299 of 2007 (Regulations 42 to 61), as amended by S.I. No. 732 of 2007 and S.I. No. 2 of 2020. The headline periods look alike, but the details differ:
- Ireland sets a period for each type of equipment in Schedule 1. LOLER sets 6 or 12 months but lets you follow an examination scheme drawn up by a competent person instead. In Ireland, a scheme is only an option in premises used mainly to generate, transform or switch electricity.
- Lifting equipment on Irish construction sites needs a weekly examination by the user.
- Schedule 1, Part C sets fixed test intervals, such as every 4 years for mobile cranes and winches.
- Excavators, telehandlers and backhoe loaders used for object handling need a signed certificate of safe working loads from a competent person before first use (Reg. 55).
How often: 6 months, 12 months and 4-yearly tests
Schedule 1, Part B gives the maximum period between thorough examinations. Your competent person can set a shorter one, but must then give the owner and user the reason in writing (Reg. 53(2)).
| Equipment (Schedule 1, Part B) | Maximum period |
|---|---|
| Lifting accessories – chains, ropes, slings, rings, hooks, shackles, clamps, swivels, spreader beams and frames, vacuum lifting devices | 6 months |
| Hoist or lift; suspended access equipment; mast climbing work platform; MEWP; tower crane climbing rig; patient hoist | 6 months |
| Other lifting machines for persons | 6 months |
| Fork lift truck or telehandler, including interchangeable accessories | 12 months (6 if used to lift persons) |
| Crane; vehicle lifting table; winch; tailboard goods lift; supports for lifting equipment; other lifting machines for materials | 12 months |
Part C adds tests as part of the thorough examination: every 4 years for mobile cranes and winches, after each assembly of a tower crane, before first use of fixed lifting equipment, and after any substantial alteration or repair affecting strength or stability. Part D lists items outside these rules, such as pallet trucks, bottle jacks and tractor hitches, which still need inspecting under Regulation 30.
The periodic cycle is not the only trigger. A competent person must also examine or inspect the equipment:
- before first use, with a certificate of test and examination for fixed equipment (Reg. 52(1)(a)). A new CE-marked mobile machine can rely on the manufacturer's documentation instead, and its first period runs from the date of first use (Reg. 52(2), as amended in 2020);
- after a repair or alteration relevant to safe operation, before the item goes back into service (Reg. 52(1)(c));
- after installation, or after assembly at a new site, where safety depends on how the item is installed (Reg. 30(a)). The same applies after exceptional circumstances such as an accident, a storm or a long lay-up (Reg. 30(b)).
Defects, deadlines and taking equipment out of use
When an examination finds the equipment is only safe once repaired, Regulation 53 requires the competent person to:
- tell the owner and user in writing;
- for a defect that is not yet dangerous, give the period within which it must be repaired;
- where immediate cessation of work has been advised, send a copy of the report to the HSA within 20 days.
Any conditions written on the report bind the employer (Reg. 52(1)(d)). The HSA's guidance adds that repairs should not be carried out during the statutory examination: the report must reflect the condition as found.
In practice: tag the item, take it out of use and record the defect with its fix-by date. Release it only after the competent person has re-examined it following the repair. A GA1 listing a defect, with nothing recorded after it, cannot show the item was made safe.
Weekly checks on construction sites
Regulation 43(1)(f) requires lifting equipment used on a construction site to be examined weekly by the user. The results must be recorded and kept available for an inspector for 3 months. It is often done by the machine operator. The HSA's guide to the work equipment regulations says the check is narrower than the statutory examination. It should include a full functional test, including the limit switches, but no overload testing. It also lists what to look at:
- the rated capacity indicator;
- ropes, chains, hooks and the structure;
- hydraulic and electrical systems and fuel lines;
- brakes, cab and controls.
The GA2 form follows the same checklist.
Since April 2020, Regulation 43 does not apply to excavators, telehandlers and backhoe loaders used for object handling, which are covered by Regulation 55. Keeping those machines in the weekly round costs little: agree this with your PSCS rather than rely on the exemption.
Worked example: a 12-month examination calendar for a small fleet
Example (fictitious): a groundworks contractor owns five items or sets. It reviews its register on 21 October 2026, and each next date is the last examination plus the Schedule 1 period.
| Item | Period | Last GA1 | Next due |
|---|---|---|---|
| Telehandler, used with a man basket | 6 m | 12/05/2026 | 12/11/2026 – 22 days left |
| Mobile crane 25 t | 12 m | 10/03/2026 | 10/03/2027 (test due 02/04/2027) |
| Four 2-leg chain slings | 6 m | 03/09/2026 | 03/03/2027 |
| Ten bow shackles | 6 m | 15/04/2026 | 15/10/2026 – overdue 6 days |
| Scissor lift (MEWP) | 6 m | 28/07/2026 | 28/01/2027 |
The shackles were on another site when the slings were examined in September, so they missed the round. They must not be used until they are examined. If that happens on 23 October 2026, their next dates are 23 April and 23 October 2027.
| Month | Due | Exams |
|---|---|---|
| Nov 2026 | Telehandler | 1 |
| Jan 2027 | Scissor lift | 1 |
| Mar 2027 | Chain slings; mobile crane | 2 |
| Apr 2027 | Shackles (+ crane 4-yearly test) | 1 |
| May 2027 | Telehandler | 1 |
| Jul 2027 | Scissor lift | 1 |
| Sep 2027 | Chain slings | 1 |
| Oct 2027 | Shackles | 1 |
| Nov 2026 – Oct 2027 | 9 |
Two easy wins: the crane's 4-yearly test falls 23 days after its March examination, so doing both on 10 March 2027 saves a visit and moves the next test to March 2031. And examining the shackles early, with the slings on 3 March, puts all accessories back on one round – an earlier examination simply restarts the clock.
Hired-in equipment: what to ask the hire company for
A firm that hires out lifting equipment must itself meet the examination and register duties in Regulations 52 and 54 (Reg. 59). For mobile equipment, the report must travel with the machine (Reg. 54(1)(c)). Before a hired machine starts work, check:
- a copy of the current report of thorough examination, whose ID mark matches the machine on site;
- that the latest date for the next examination is after the planned off-hire date;
- that the report covers the interchangeable accessories supplied with it (forks, jib, basket), and that any slings or shackles come with their own reports;
- the Reg. 55 safe working load certificate if an excavator or telehandler will be used for object handling;
- who does the weekly check on site – the regulation puts it on the user, normally you.
If you hire machines out yourself, a plant hire workbook that flags exams falling due during a hire catches this before the machine leaves the yard.
The register, the reports and how long to keep them
Regulation 54 requires a register of lifting equipment and lifting accessories. It must show each item, its distinguishing number and the dates of first use and of the last thorough examination, and be available to an inspector. The HSA confirms the register can be electronic or printed. Each report must be kept where the equipment is used: at the workplace, at the site office (or the contractor's business address), or, for mobile equipment, on the machine and at the owner's address.
Regulation 54 sets no retention period for reports; weekly records must be kept for 3 months and Regulation 30 inspection records for 5 years. Keeping every GA1 for the life of the item is the simplest rule.
Finally, a thorough examination is not maintenance – the HSA guidance treats them as separate. Servicing to the manufacturer's intervals belongs in a preventive maintenance schedule for your machines and plant, while the statutory examinations stay in the lifting register.
Frequently asked questions
How long is a GA1 valid for?
A GA1 has no fixed validity of its own. It states the latest date for the next thorough examination, which can be no later than the Schedule 1 period – 6 or 12 months for most equipment – and can be earlier if the competent person sets a shorter period or finds a defect.
Who can carry out a GA1 examination?
A competent person: someone with sufficient training, experience and knowledge for the equipment, as defined in section 2 of the Safety, Health and Welfare at Work Act 2005. It can be an employee, but the HSA's guidance says that person must be able to exercise independent judgement.
Does a pallet truck or bottle jack need a GA1?
No. Schedule 1, Part D takes pallet trucks, bottle jacks, tractor hitches, escalators and some small platform lifts out of the thorough examination rule. They are still work equipment, so they need inspection and maintenance under Regulations 30 and 31.
Can I download a blank GA1 form?
Yes – the HSA publishes the GA1 and GA2 as PDFs on its forms page. The competent person who examines the equipment completes and signs it, and the person receiving the report signs for it. A report in another format is acceptable if it contains the Schedule 1, Part E particulars.
Do new slings and shackles need a certificate before first use?
Yes. Under Regulation 57, a chain, wire rope sling or other lifting accessory must not be used until a competent person has tested and examined it and a signed certificate stating its safe working load has been obtained. It must also be marked with its SWL and an ID. Fibre rope slings need the manufacturer's SWL information instead.
What is a GA3 form?
The GA3 is the HSA's template for inspections of work equipment for work at height under Regulation 119 – scaffolds, working platforms, ladders and fall protection. It does not replace a GA1 or GA2 for lifting equipment.
Sources
- Law Reform Commission – S.I. No. 299 of 2007, revised (General Application Regulations), Schedule 1 – Part B periods, Part C tests, Part D exclusions, Part E report contents; revised text, up to date to 13 October 2026
- Law Reform Commission – S.I. No. 299 of 2007, revised, Regulation 52 (examination and testing) – before first use, after repair, period from date of first use
- Law Reform Commission – S.I. No. 299 of 2007, revised, Regulation 53 (reports by competent persons) – repairs in writing, 20 days to the HSA, shorter period
- Law Reform Commission – S.I. No. 299 of 2007, revised, Regulation 54 (records and register)
- Law Reform Commission – S.I. No. 299 of 2007, revised, Regulation 43 (cranes; weekly examination on construction sites) – 43(1)(f) weekly, 3 months; 43(2) Regulation 55 machines
- Law Reform Commission – S.I. No. 299 of 2007, revised, Regulation 30 (inspection of work equipment) – installation, exceptional circumstances, 5-year records
- Irish Statute Book – S.I. No. 299 of 2007 as made
- Irish Statute Book – S.I. No. 2 of 2020, General Application (Amendment) Regulations 2020 – in force 1 April 2020; amended Regulations 43, 52 and 55
- Health and Safety Authority – Forms (GA1, GA2, GA3)
- Health and Safety Authority – Form GA1, Report of Thorough Examination (revision 2012) – "This is not an approved or statutory form"
- Health and Safety Authority – Form GA2, Report of Weekly Examination
- Health and Safety Authority – Form GA3, inspections of work equipment for work at height
- Health and Safety Authority – Guide to the General Application Regulations 2007, Chapter 2 of Part 2: Use of Work Equipment (2010 update) – weekly examination content, competent person independence, register electronic or printed
- Irish Statute Book – Safety, Health and Welfare at Work Act 2005, section 2 (competent person)
- legislation.gov.uk – Lifting Operations and Lifting Equipment Regulations 1998 (UK)
- legislation.gov.uk – Lifting Operations and Lifting Equipment Regulations (Northern Ireland) 1999